Roadway Resurfacing (Paving)

Roads to Be Resurfaced in 2022

Name From To Treatment
Livingston Street Main Street #135 Livingston Street Reclaim and 5" pave
Royal Crest Circle East Street Dead-End Reclaim and 4" pave
Cayuga Road Catamount Road Dead-End Reclaim and 4" pave
Starr Avenue Martha Road #55 Starr Avenue 2" mill and overlay
Old Main Street Main Street Alpine Avenue 2" mill and overlay
Oxford Street Beech Street Cul-de-sac 2" mill and overlay
Miles Road Brown Street Dead-End 2" mill and overlay

Roadway Microsurfacing

Microsurfacing is a protective seal coat which extends the life of pavement. It is a thin, tough layer of asphalt emulsion blended with finely crushed stone for traction. This is a cost-effective method to renew the road surface and seal minor cracks and other irregularities.

As part of The Town’s pavement management program, it plans to microsurface the following roads:

  • South Elizabeth Street
  • South Rhoda Street
  • South Amos Street
  • Knollwood Road
  • Charm Road
  • Strang Street

(These streets may change due to budget constraints and an analysis of road condition)


Paving Updates

September 21, 2022

The Town’s contractor, Indus, is currently working throughout the town performing crack sealing on the various roads. This is part of the Town of Tewksbury’s overall pavement management program. If you have any questions, please contact the Town’s Project Manager, Arthur G. Markos, at 978 640-4440 x237 or by emailing amarkos@tewksbury-ma.com.

September 19, 2022 Update

Starting Tuesday, September 20, 2022, the Town’s contractor, EJ Paving, will begin road resurfacing work on Livingston Street from Main Street to Wildwood Street. Crews will be working for the remainder of the week. There will be a detour set up for all through traffic, however, the area will be open to abutters and businesses. Traffic Control Officers will be present to direct traffic for the duration of the work, but delays are likely. We ask travelers to give themselves extra time and thank you in advance for your patience during the work. If you have any questions or concerns, please contact the Town’s Project Manager, Arthur G. Markos, at 978-640-4440 x237 or by emailing amarkos@tewksbury-ma.gov.

Detour Map

September 8, 2022 Update

The Town’s Contractor, EJ Paving, will be paving the top coat of pavement on Cayuga Road and Royal Crest Circle on Friday, September 9, 2022.  Please be advised that roads will have limited access during this time and residents are advised to park all vehicles off of the roadway to allow for access by roadway paving crews and equipment.  Paving is anticipated to begin at approximately 11:30AM on Cayuga Road and will proceed to Royal Crest Circle once completed.  If you have any questions or concerns, please contact Andrew Stack at astack@tewksbury-ma.gov or by calling (978) 640-4440, ext. 256.

August 31, 2022 Update

The Town’s coPaving Update 8312022ntractor, EJ Paving, will begin paving the asphalt berm (curbing) on Royal Crest Circle and Cayuga Road on Thursday, September 1, 2022.  Residents are advised to park vehicles off of the roadway during work hours (typically 7:00AM to 4:30PM) to allow for access to the roadway edge by paving crews and equipment.  The work is anticipated to begin on Royal Crest Circle approximately mid-morning and will proceed to Cayuga Road once completed.  Asphalt berm paving work may extend into Friday, September 2, 2022, if needed.  The final roadway surface is to be paved at a later date (to be determined).

August 25, 2022 Update

The Town’s contractor, EJ Paving, will be applying the top final layer of pavement on Old Main Street near Wamesit Island. The work will begin this afternoon and should be completed by the end of the day.

July 26, 2022 UpdatePavingUpdate20220726

The Town’s Contractor, EJ Paving, will be paving the topcoat of pavement on the following roads: Oxford Street, Miles Road and sections of Starr Road and Old Main Street, on Wednesday, July 27, 2022, and Thursday July 28, 2022 (Weather Permitting). Please be advised that roads will have limited access during this time, but traffic control officers will be there to assist if needed. If you have any questions or concerns, please contact The Town’s Project Manager, Arthur G. Markos, by email at amarkos@tewksbury-ma.gov or by calling (978) 640-4440, ext. 237. More Info available at www.tewksbury-ma.gov/paving.

July 11, 2022 Update

The Town of Tewksbury’s contractor, EJ Paving, will begin the process of roadway paving on July 11, 2022 (weather permitting). Work hours  will typically be between 7:00 am and 4:30 pm Monday through Friday. Please be advised that roads will have limited access during this time. The entire project will take approximately 2-3 weeks to complete. If you have any sprinkler heads near the roadway please mark out clearly, so that work crews can avoid causing damage.

We appreciate your cooperation and patience in advance. If you have any questions or concerns please contact The Town’s Project Manager, Arthur G. Markos, by email at amarkos@tewksbury-ma.gov or by calling (978) 640-4440, ext. 237.