Project Number
PW-22-27
Project Description
This project involves replacement of the existing 2” cast iron and 2” plastic water main with a new 8” ductile iron water main, new HDPE water service connections, new fire hydrants, and new valves. This new water main will provide increased structural integrity, greater flow capacity, and increased fire protection capabilities.
Project Location
The project area includes School Street, Bell Road, and Cottage Street.
School Street Locus Map
Anticipated Construction Dates
Work is anticipated to begin in mid-to-late July 2022. Once excavation work begins, it is anticipated to take approximately three weeks to complete construction.
Typical Work Hours
Work hours are typically Monday to Friday from 7:00AM to 3:30PM excluding holidays.
Roadway Closure/Detour Information
Depending on where the work zone is located each day, residents may need to access their residences from either the South Street end or the Glenwood Road end of School Street due to daily roadway closures during construction hours. Franklin Street or State Street can be utilized as a detour route during construction. Roadway closure signs will be posted, and police details will be on-site during construction hours.
Project Updates
Project Updates will be posted here once work begins.
Contractor
Cedrone Trucking, Inc. of Billerica, MA
Project Contacts
Andrew Stack, Project Manager, Tewksbury DPW (978) 640-4440 x256 astack@tewksbury-ma.gov